Plant Title:
Haripur 412 MW Combined Cycle Power Plant
Plant Location:
Haripur, Bandar, Narayanganj
Fuel:
Natural Gas
EPC Contract Price:
349 Million USD
Financed By:
Japan International Cooperation Agency (JICA) and GOB.
Total Capacity:
412 MW (Net)
EPC Contractor:
Marubeni Corporation, Japan.
| Name | GT |
| Capacity | 279 MW |
| Installation capacity | 279 MW |
| COD | 6th April 2014 |
| Fuel type | Natural Gas |
| Manufacturar | Mitsubishi Heavy Industries (MHI) Ltd.,Japan |
| Thermal Efficiency | 56% , CC Mode |
| Site Image | |
| Site Image | ![]() |
| Name | ST |
| Capacity | 149 MW |
| Installation capacity | 149 MW |
| COD | 6th April 2014 |
| Fuel type | - |
| Manufacturar | Fuji Electric co. ltd. , Japan |
| Thermal Efficiency | - |
| Site Image | ![]() |
| Site Image | ![]() |
| Executive Agency | Electricity Generation Company of Bangladesh Ltd. |
| EGCB Cost | 50.00 Lakh |
| DPA Cost | 283,570.95 Lakh |
| GOB Cost | 28,394.78 Lakh |
| Total Costs | 312,015.73 Lakh |
| Signing Date | 2011-02-09 |
| Configuration | 1GTG:1 HRSG:1STG |
| Operation Date | 2014-04-06 |
| Capacity | 412 MW (Net) |
| LTSA | 1st LTSA 1st Long Term Service Agreement (LTSA) was signed on 29 Oct 2014 between EGCB and Marubeni Hitachi Power System (MHPS), Japan. Performance Start Date: 29 January 2017 Expired Date: Date of Completion of 1st TI i.e., 15 November 2018 2nd LTSA 2nd Long Term Service Agreement (LTSA) was signed on 29 May 2019 between EGCB and Marubeni Power & Infrastructure Systems Corporation (MPSC), Japan for 10 (Ten) years. |
| Land use agreement | Agrement -1 on 2015 |
| Power purchese agreement | - |