কনটেন্টটি শেষ হাল-নাগাদ করা হয়েছে: সোমবার, ২৭ এপ্রিল, ২০২৬ এ ০২:২৪ PM
কন্টেন্ট: পাতা


Current Dependable Capacity (Effective From 20/12/2025, 00:00 H) 210 MW.
Sl. No. | Dependable Capacity (MW) | Effective Date |
01 | 199.8882 | 05.02.2012 (COD) |
02 | 209.5437 | 06.05.2015 |
03 | 210 | 22.09.2018 |
04 | 209.356 | 12.07.2020 |
05 | 208.615 | 22.10.2021 |
06 | 210 | 26.11.2022 |
07 | 210 | 09.12.2023 |
| 08 | 208.137 | 12.12.2024 |
09 | 210 | 20.12.2025 |
| Unit Name | GT-1 |
| Unit Description | Machine No: GT 171, AIR IN: 35°C, Altitude: 4.5 Meter Above MSL, Base: 108.600 MW (Gross), Compressor Stages: 17, RPM: 3000, Power Turbine Stages: 3, RPM: 3000 COD: 05/02/2012 Fuel Type: Natural Gas Manufacturar: BHEL Thermal Efficiency: 31% (Appx.) |
| Unit Name | GT-2 |
| Unit Description | Machine No: GT 172, AIR IN: 35°C, Altitude: 4.5 Meter Above MSL, Base: 108.600 MW (Gross), Compressor Stages: 17, RPM: 3000, Power Turbine Stages: 3, RPM: 3000 COD: 05/02/2012 Fuel Type: Natural Gas Manufacturar: BHEL Thermal Efficiency: 31% (Appx.) |
| Executive Agency | Electricity Generation Bangladesh PLC. |
| EGCB Cost | 0.00 |
| DPA Cost | 77,000.00 |
| GOB Cost | 47,563.00 |
| Total Costs | 124,563.00 |
| Signing Date | 2007-01-31 |
| Configuration | 1GT:1GT |
| Operation Date | 2012-02-05 |
| Capacity | 210 MW |
| LTSA | 14 LTSA Long Term Service Agreement (LTSA) signed on 31-10-2013 for a period of six (6) years with (1) BHEL, India for Generation and BOP portion and with (2) BGGTS for CI/HGPI/MI of GT portion. |