সোনাগাজী ৭৫মেঃওঃ সৌর বিদ্যুৎ কেন্দ্র, সোনাগাজী, ফেনী
Plant Title:
Sonagazi 75 MW Solar Power Plant
Plant Location:
Purba Borodhali, Charchandia, Sonagazi, Feni
EPC Contract Price:
70 million USD
Financed By:
IDA (World Bank) and GOB.
Total Capacity:
75 MW (Net)
EPC Contractor:
Trina Solar-HYDC JV, China.
Owner’s Engineer:
TUV SUD South Asia and TUV SUD Bangladesh JV
| Plant type | Solar Power Plant |
| Net Capacity | 75 MW ac |
| Installation Capacity | 96.34 MW dc |
| COD | 1st April 2024 (Under declaration) |
| Renewable Energy Source: | Natural Solar Irradiation |
| Manufacturer | PV Module: Trina Solar, China Central Inverter: Sungrow, China |
| PV Module Efficiency | 22% (as per manufacturer’s Data Sheet) |
| Site Image of Main Installations |
|
| PV modules and Inverter Stations |
|
| Substation |
|
| Evacuation Transformers |
|
| 230KV Control Building |
|
| 33KV Control Building |
|
| 230 KV Transmission line (13.33 KM) |
|
| Plant Night View |
|
| Executive Agency | Electricity Generation Company of Bangladesh Ltd. (EGCB) |
| EGCB Cost | Tk. 62.61 Crore |
| DPA Cost | Tk. 725.63 Crore |
| GOB Cost | Tk. 87.54 Crore |
| Total Costs | Tk. 875.78 Crore |
| Project Period | July/2019 - June/2024 |
| EPC Contract Signing Date | June 15, 2021 |
| Power Evacuation to Grid | 230KV bus at Mirshari 230/33KV Grid Substation, PGCB |
| Back Feed Date | February 19, 2024 |
| Power Delivered to Grid (First) | February 24, 2024 |
| Dependable Capacity | - |
| Operation and Maintenance (O&M) Contractor for 3 years | EPC (Trina Solar- HYDC JV, China) |
| Power Purchase Agreement (PPA) | Under progress |